A lead time is the latency between the initiation and completion of a process. For example, the lead time between the placement of an order and delivery of new cars by a given manufacturer might be between two weeks and six months, depending on various particularities. One business dictionary defines "manufacturing lead time" as the total time required to manufacture an item, including order preparation time, queue time, setup time, run time, move time, inspection time, and put-away time. For make-to-order products, it is the time between release of an order and the production and shipment that fulfill that order. For make-to-stock products, it is the time taken from the release of an order to production and receipt into finished goods inventory.
Supply chain management A conventional definition of lead time in a supply chain management context is the time from the moment the customer places an order (the moment the supplier learns of the requirement) to the moment it is ready for delivery. In the absence of finished goods or intermediate (work in progress) inventory, it is the time it takes to actually manufacture the order without any inventory other than raw materials. The Chartered Institute of Procurement & Supply identifies "total lead time" as a combination of "internal lead time" (the time required for the buying organization's internal processes to progress from identification of a need to the issue of a purchase order) and "external lead time" (the time required for the supplying organization's processes, including any development required, manufacture, dispatch and delivery). The lead time applicable to material flows within a supply chain may be paralleled by the concept of "information lead time". Mason-Jones and Towill report that reductions in both material flow lead time and information lead time are necessary to secure supply chain performance improvements. Several writers have referred to the importance of "information enriched supply chains" in this context.
Manufacturing In the manufacturing environment, lead time has the same definition as that used in supply chain management, but it includes the time required to ship the parts from the supplier. Shipping time is included because the manufacturing company needs to know when the parts will be available for material requirements planning purposes. It is also possible to include within lead time the time it takes for a company to process and have the part ready for manufacturing once it has been received. The time it takes a company to unload a product from a truck, inspect it, and move it into storage ("put-away time") is not trivial. With tight manufacturing constraints or when a company is using Just In Time manufacturing, it is important for supply chain to know how long their own internal processes take. Lead time consists of:
Preprocessing Lead Time (also known as "planning time" or "paperwork"): the time required to release a purchase order (if you buy an item) or create a job (if you manufacture an item), from the time you learn of the requirement. Processing Lead Time: the time required to procure or manufacture an item. Postprocessing Lead Time: the time to make a purchased item available in inventory from the time you receive it (including quarantine, inspection, etc.) For example, Company A needs a part that can be manufactured in two days once Company B has received an order. It takes three days for company A to receive the part once shipped, and one additional day before the part is ready to go into manufacturing.
If Company A's Supply Chain calls Company B they will be quoted a lead time of two days for the part. If Company A's Manufacturing division asks the Supply Chain division what the lead time is, they will be quoted five days since shipping will be included. If a line worker asks the Manufacturing Division boss what the lead time is before the part is ready to be used, it will be six days because setup time will be included.
Possible ways of shortening lead time To best meet the customer needs, a company should work towards the shortest possible lead time in manufacturing, production, and delivery. It can be helped by:
Improving each processing step's efficiency through minimizing waste, quickly resolving any bottlenecks. Applying production leveling (Heijunka) to both supply chain management and production process steps. Automating all possible actions along the process. Reducing the length of the idle (waiting) process stages, as these are often the most wasteful and can be the easiest ones to tackle for a start.
Order lead time When talking about Order Lead Time (OLT) it is important to differentiate between the definitions that may exist around this concept. Although they look similar, there are differences between them that help the industry to model the order behavior of their customers. The four definitions are :
The Actual Order Lead Time (OLTActual) refers to the time which elapses between the receipt of the customer's order (Order Entry Date) and the delivery of the goods." The Requested Order Lead Time (OLTRequested) represents the time between the Order Entry Date and the customer requested delivery date; this measurement could help the company to understand the order behavior of the customers and help to design profitable models to fulfill customer needs. The Quote Order Lead Time (OLTQuote) is the agreed time between the Order Entry Date and the supplier's committed deliver date of goods as stipulated in a supply chain contract. The Confirmed Order Lead Time (OLTConfirmed) represents the time between the Order Entry Date and the supplier's confirmed delivery date of goods.
OLT formulas OLTRequested = Wish Date – Order Entry Date The OLTRequested will be determined by the difference between the date the customer wants the material in his facilities (wish date) and the date when they provided its order to the supplier.
OLTQuote = Quote Date – Order Entry Date The OLTQuote will be determined by the difference between the date the customer agree to receive the material in their facilities (Quote date) and the date when the order is provided to the supplier.
OLTActual = Delivery Date – Order Entry Date The OLTActual will be determined by the difference between the day the provider deliver the material (Delivery date) and the date when they enter the order in the system.
… excerpt ends here. Continue reading the full article.