Levelling or leveling (American English; see spelling differences) is a branch of surveying, the object of which is to establish or verify or measure the height of specified points relative to a datum. It is widely used in geodesy and cartography to measure vertical position with respect to a vertical datum, and in construction to measure height differences of construction artifacts. In photolithography, the same term is used in a lithography machine calibration step measuring or calibrating wafer surface height with respect to a reference.
Optical levelling
Optical levelling, also known as spirit levelling and differential levelling, employs an optical level, which consists of a precision telescope with crosshairs and stadia marks. The cross hairs are used to establish the level point on the target, and the stadia allow range-finding; stadia are usually at ratios of 100:1, in which case one metre between the stadia marks on the level staff (or rod) represents 100 metres from the target. The complete unit is normally mounted on a tripod, and the telescope can freely rotate 360° in a horizontal plane. The surveyor adjusts the instrument's level by coarse adjustment of the tripod legs and fine adjustment using three precision levelling screws on the instrument to make the rotational plane horizontal. The surveyor does this with the use of a bull's eye level built into the instrument mount.
Procedure
The surveyor looks through the eyepiece of telescope while an assistant holds a vertical level staff which is graduated in inches or centimeters. The level staff is placed vertically using a level, with its foot on the point for which the level measurement is required. The telescope is rotated and focused until the level staff is plainly visible in the crosshairs. In the case of a high accuracy manual level, the fine level adjustment is made by an altitude screw, using a high accuracy bubble level fixed to the telescope. This can be viewed by a mirror whilst adjusting or the ends of the bubble can be displayed within the telescope, which also allows assurance of the accurate level of the telescope whilst the sight is being taken. However, in the case of an automatic level, altitude adjustment is done automatically by a suspended prism due to gravity, as long as the coarse levelling is accurate within certain limits. When level, the staff graduation reading at the crosshairs is recorded, and an identifying mark or marker placed where the level staff rested on the object or position being surveyed. A typical procedure for a linear track of levels from a known datum is as follows. Set up the instrument within 100 metres (110 yards) of a point of known or assumed elevation. A rod or staff is held vertical on that point and the instrument is used manually or automatically to read the rod scale. This gives the height of the instrument above the starting (backsight) point and allows the height of the instrument (H.I.) above the datum to be computed. The rod is then held on an unknown point and a reading is taken in the same manner, allowing the elevation of the new (foresight) point to be computed. The difference between these two readings equals the change in elevation, which is why this method is also called differential levelling. The procedure is repeated until the destination point is reached. It is usual practice to perform either a complete loop back to the starting point or else close the traverse on a second point whose elevation is already known. The closure check guards against blunders in the operation, and allows residual error to be distributed in the most likely manner among the stations. Some instruments provide three crosshairs which allow stadia measurement of the foresight and backsight distances. These also allow use of the average of the three readings (3-wire leveling) as a check against blunders and for averaging out the error of interpolation between marks on the rod scale. The resulting distance calculations can also be used to compensate for errors produced by unevenly spaced backsight and foresight readings. The two main types of levelling are single-levelling as already described, and double-levelling (double-rodding). In double-levelling, a surveyor takes two foresights and two backsights and makes sure the difference between the foresights and the difference between the backsights are equal, thereby reducing the amount of error. Double-levelling costs twice as much as single-levelling.
Turning a level When using an optical level, the endpoint may be out of the effective range of the instrument. There may be obstructions or large changes of elevation between the endpoints. In these situations, extra setups are needed. Turning is a term used when referring to moving the level to take an elevation shot from a different location. To "turn" the level, one must first take a reading and record the elevation of the point the rod is located on. While the rod is being kept in exactly the same location, the level is moved to a new location where the rod is still visible. A reading is taken from the new location of the level and the height difference is used to find the new elevation of the level gun. This is repeated until the series of measurements is completed. The level must be horizontal to get a valid measurement. Because of this, if the horizontal crosshair of the instrument is lower than the base of the rod, the surveyor will not be able to sight the rod and get a reading. The rod can usually be raised up to 25 feet high, allowing the level to be set much higher than the base of the rod.
Trigonometric levelling
The other standard method of levelling in construction and surveying is called trigonometric levelling, which is preferred when levelling "out" to a number of points from one stationary point. This is done by using a total station, or any other instrument to read the vertical, or zenith angle to the rod, and the change in elevation is calculated using trigonometric functions (see example below). At greater distances (typically 1,000 feet and greater), the curvature of the Earth, and the refraction of the instrument wave through the air must be taken into account in the measurements as well (see section below).
Ex: an instrument at Point A reading to a rod at Point B a zenith angle of < 88°15'22" (degrees, minutes, seconds of arc) and a slope distance of 305.50 feet not factoring rod or instrument height would be calculated thus: