Since 2024, dozens of local community-led protest campaigns have emerged in opposition to AI data centers.
Motivations Organized opposition to AI data centers has been driven by concerns about their impact on nearby residents, in the form of increased energy use, energy costs, noise pollution, air pollution, and water waste. Opposition sentiment is widespread with a Gallup poll conducted in March 2026 showing that 70% of respondents oppose the construction of new AI data centers in their neighborhood.
Impact In 2025, local opposition to AI data centers led to the delay or cancellation of projects totalling US$156 billion.
Specific protests and outcomes in the United States According to Data Center Watch, there are has been a wave of dozens of protests against AI data centers since 2022. Below is a non-exhaustive list of some notable examples.
Goodyear and Buckeye, Arizona: Tract proposal In Goodyear and Buckeye, Arizona, a $14 billion project by developer Tract was withdrawn after local authorities blocked necessary rezoning in response to pressure from resident organizers. Opponents' stiff resistance is due to concerns over building heights, noise pollution, and the potential strain on local utilities. However, the company announced a revised project near the Buckeye airport in August 2024, with the backing of local officials and the mayor.
Peculiar, Missouri: Diode Ventures Harper Road Technology Park proposal In Peculiar, Missouri, residents from the group "Peaceful Peculiar" organized to stop a data center proposal from Diode Ventures called Harper Road Technology Park. Citing concerns around noise and light pollution, health, environmental impacts, jobs, property values, and energy use, organizers attended local planning and zoning meetings in large numbers and lobbied councilors to reject the proposal. Ultimately, the city council unanimously rejected the proposal in September 2024.
Chesterton, Indiana: Provident Realty Advisors proposal In Chesterton, Indiana, the Texas-based company Provident Reality Advisors applied for a $1.3 billion construction of a data center complex on the Brassie Golf Club property. Provident Realty Advisors wanted to purchase the 200 acres owned by PPM Chesterton LLC in 2024 order to build a data center complex, with eight buildings and an end user of a hyperscaler. The Town Council of Chesterton released a statement saying that they would never support this project, at least not at the scale and location it was planned for. They cited fears of added noise for locals, electrical or water management concerns, the intrusiveness of a data center built next to houses, and more. Provident released a statement shortly after rescinding their plan, because it was clear than the town of Chesterton would not support them.
Cascade Locks, Oregon: Roundhouse Digital Infrastructure proposal Startup data center developer Roundhouse Digital Infrastructure had planned to build out a 10-megawatt data center using a vacant industrial building and nearby 10-acre site in the Port of Cascade Locks, Oregon. After significant organized community opposition, the project was abandoned.
Fort Worth, Texas: WUSF 5 Rock Creek East proposal In September 2024, the City Council of Fort Worth, Texas approved a zoning change that would allow construction of a data center. In responses, neighbors mounted opposition citing concerns about traffic, light pollution, energy consumption, water use, and noise issues if the data center were to be built. In response to extensive public comments opposing a tax break for the data center, a city councilor withdrew his motion to approve the tax break. As of April, 2026, the future of the project is still uncertain.
Santa Clara, California: GI partners proposal GI partners sought to build a new AI data center in Santa Clara, California, which is already home to many data centers, by acquiring a conditional permit use that would have allowed the developer to knock down a property and replace it with a data center. To obtain this permit they were required to go before members of the Planning Commission. Ultimately, the project was delayed with the Planning Commission requiring GI partners to do more public outreach.
Salem, Oregon: Verrus proposal A $5.1 billion dollar data center proposal was discussed at a Salem City Council meeting. Verrus company representatives left the meeting after learning protestors brought a guillotine to a demonstration outside the meeting. The city council voted unanimously to develop a moratorium policy on future data center proposals to be presented by December 2026.
Virginia
Richmond: DC Blox proposal After residents organized to lobby the municipal government to block the proposal to avoid noise pollution and higher energy use, commissioners denied the company's permit.
Catlett Station: Headwaters site proposal In Catlett, Virginia, developer Headwaters proposed construction of a data center complex just north of the town in 2020. In response, a residents' organization called "Protect Catlett" was formed to oppose the project. Arguments against the data center involved its impacts on water and power availability, its noise as a residential disturbance, and its destruction of historic and community heritage buildings. Arguments in favor cited job creation and $20 million in local tax revenue if the project were to go through. Protect Catlett utilized town halls and public comments to mobilize opposition to the project. They also dedicated time to educating other residents about the project's negative impacts and canvassing door-to-door in order to garner even more opposition to the project. Ultimately, after fervent opposition from most town residents, the project was canceled by the town and the developer.