ArticleslgStudy

engineering

Program evaluation and review technique

Program evaluation and review technique is a engineering topic covered in the lgStudy science library. This page brings together a partial reference excerpt, illustrations, worked examples, real-world applications and a short study plan, so you can understand Program evaluation and review technique rather than just read about it. In short: The program evaluation and review technique (PERT) is a statistical tool used in project management, which was designed to analyze and represent the tasks involved in completing a given project. PERT was originally developed by Charles E.

Program evaluation and review technique — main illustration
Program evaluation and review technique — illustration

Key takeaways

  • Program evaluation and review technique belongs to engineering; place it in that map before memorising details.
  • Learn the definition first, then one example that makes the definition concrete.
  • Connect Program evaluation and review technique to a quantity you can measure, compute or draw — that is where exam questions come from.
  • Reproduce the core statement of Program evaluation and review technique from memory before moving on to harder problems.

Reference excerpt

The program evaluation and review technique (PERT) is a statistical tool used in project management, which was designed to analyze and represent the tasks involved in completing a given project. PERT was originally developed by Charles E. Clark for the United States Navy in 1958; it is commonly used in conjunction with the Critical Path Method (CPM), which was also introduced in 1958.

Overview PERT is a method of analyzing the tasks involved in completing a project, especially the time needed to complete each task, and to identify the minimum time needed to complete the total project. It incorporates uncertainty by making it possible to schedule a project while not knowing precisely the details and durations of all the activities. It is more event-oriented than start- and completion-oriented, and is used more for projects where time is the major constraint rather than cost. It is applied to very large-scale, one-time, complex, non-routine infrastructure projects, as well as R&D projects. PERT offers a management tool, which relies "on arrow and node diagrams of activities and events: arrows represent the activities or work necessary to reach the events or nodes that indicate each completed phase of the total project." PERT and CPM are complementary tools, because "CPM employs one time estimation and one cost estimation for each activity; PERT may utilize three time estimates (optimistic, expected, and pessimistic) and no costs for each activity. Although these are distinct differences, the term PERT is applied increasingly to all critical path scheduling."

History PERT was developed primarily to simplify the planning and scheduling of large and complex projects. It was developed by the United States Navy Special Projects Office, Lockheed Aircraft, and Booz Allen Hamilton to support the Navy's Polaris missile project. It found applications throughout industry. An early example is the 1968 Winter Olympics in Grenoble which used PERT from 1965 until the opening of the 1968 Games. This project model was the first of its kind, a revival for the scientific management of Frederick Taylor and later refined by Henry Ford (Fordism). DuPont's CPM was invented at roughly the same time as PERT.

Initially PERT stood for Program Evaluation Research Task, but by 1959 was renamed. It had been made public in 1958 in two publications of the U.S. Department of the Navy, entitled Program Evaluation Research Task, Summary Report, Phase 1. and Phase 2. both primarily written by Charles F. Clark. In a 1959 article in The American Statistician, Willard Fazar, Head of the Program Evaluation Branch, Special Projects Office, U.S. Navy, gave a detailed description of the main concepts of PERT. He explained:

Through an electronic computer, the PERT technique processes data representing the major, finite accomplishments (events) essential to achieve end-objectives; the inter-dependence of those events; and estimates of time and range of time necessary to complete each activity between two successive events. Such time expectations include estimates of "most likely time", "optimistic time", and "pessimistic time" for each activity. The technique is a management control tool that sizes up the outlook for meeting objectives on time; highlights danger signals requiring management decisions; reveals and defines both methodicalness and slack in the flow plan or the network of sequential activities that must be performed to meet objectives; compares current expectations with scheduled completion dates and computes the probability for meeting scheduled dates; and simulates the effects of options for decision— before decision.

Ten years after the introduction of PERT, the American librarian Maribeth Brennan compiled a selected bibliography with about 150 publications on PERT and CPM, all published between 1958 and 1968. For the subdivision of work units in PERT another tool was developed: the Work Breakdown Structure. The Work Breakdown Structure provides "a framework for complete networking, the Work Breakdown Structure was formally introduced as the first item of analysis in carrying out basic PERT/CPM."

Terminology

Events and activities In a PERT diagram, the main building block is the event, with connections to its known predecessor events and successor events.

PERT event: a point that marks the start or completion of one or more activities. It consumes no time and uses no resources. When it marks the completion of one or more activities, it is not "reached" (does not occur) until all of the activities leading to that event have been completed. predecessor event: an event that immediately precedes some other event without any other events intervening. An event can have multiple predecessor events and can be the predecessor of multiple events. successor event: an event that immediately follows some other event without any other intervening events. An event can have multiple successor events and can be the successor of multiple events. Besides events, PERT also tracks activities and sub-activities:

PERT activity: the actual performance of a task which consumes time and requires resources (such as labor, materials, space, machinery). It can be understood as representing the time, effort, and resources required to move from one event to another. A PERT activity cannot be performed until the predecessor event has occurred. PERT sub-activity: a PERT activity can be further decomposed into a set of sub-activities. For example, activity A1 can be decomposed into A1.1, A1.2 and A1.3. Sub-activities have all the properties of activities; in particular, a sub-activity has predecessor or successor events just like an activity. A sub-activity can be decomposed again into finer-grained sub-activities.

Time PERT defines four types of time required to accomplish an activity:

… excerpt ends here. Continue reading the full article.

Illustrations

Program evaluation and review technique: PERT network chart for a seven-month project with five milestones (10 through 50) and six activities (A through F)
PERT network chart for a seven-month project with five milestones (10 through 50) and six activities (A through F)
Program evaluation and review technique: PERT Summary Report Phase 2, 1958
PERT Summary Report Phase 2, 1958
Program evaluation and review technique: PERT Guide for Management Use, June 1963
PERT Guide for Management Use, June 1963
Program evaluation and review technique: A Gantt chart created using Microsoft Project (MSP). Note (1) the critical path is in red, (2) the slack is the black lines connected to non-critical activities, (3) since Saturday and Sunday are not work days and are thus excluded from the schedule, some bars on the Gantt chart are longer if they cut through a weekend.
A Gantt chart created using Microsoft Project (MSP). Note (1) the critical path is in red, (2) the slack is the black lines connected to non-critical activities, (3) since Saturday and Sunday are not work days and are thus excluded from the schedule, some bars on the Gantt chart are longer if they cut through a weekend.
Program evaluation and review technique: A Gantt chart created using OmniPlan. Note (1) the critical path is highlighted, (2) the slack is not specifically indicated on task 5 (d), though it can be observed on tasks 3 and 7 (b and f), (3) since weekends are indicated by a thin vertical line, and take up no additional space on the work calendar, bars on the Gantt chart are not longer or shorter when they do or don't carry over a weekend.
A Gantt chart created using OmniPlan. Note (1) the critical path is highlighted, (2) the slack is not specifically indicated on task 5 (d), though it can be observed on tasks 3 and 7 (b and f), (3) since weekends are indicated by a thin vertical line, and take up no additional space on the work calendar, bars on the Gantt chart are not longer or shorter when they do or don't carry over a weekend.

Worked examples

Example 1 — a first encounter with Program evaluation and review technique

Start with the simplest possible case. Write down what Program evaluation and review technique claims or describes in one sentence, then invent the smallest concrete situation in which that sentence is true. In engineering, the smallest case is usually a single object, a single equation or a single measurement. Check that every symbol or term in your sentence has a meaning in that case.

Example 2 — changing one variable

Take the situation from Example 1 and change exactly one quantity: double it, halve it, or set it to zero. Predict what should happen to Program evaluation and review technique before you calculate. Comparing your prediction with the result is the fastest way to find out whether you understand the idea or only the words.

Example 3 — an exam-style question

Typical questions about Program evaluation and review technique ask you to (a) state it precisely, (b) apply it to given data, and (c) explain a limitation. Practise writing all three answers in under five minutes; the third part is what separates a full-mark answer from an average one.

Applications of Program evaluation and review technique

In research
Program evaluation and review technique appears in engineering research whenever the underlying quantities have to be modelled precisely. Papers usually cite it as a starting assumption and then explore where it breaks down.
In technology and industry
Engineering practice reuses Program evaluation and review technique in design rules, simulations and safety margins. Knowing the idea lets you read a specification sheet and understand why the numbers look the way they do.
In the classroom
Program evaluation and review technique is common in secondary-school and first-year university syllabi. It links to neighbouring topics Booz Allen Hamilton, Diagrams, Engineering management, so understanding it makes those chapters shorter.
In everyday life
Look for Program evaluation and review technique outside the textbook — in sport, cooking, traffic, electronics or the sky above you. An example you found yourself is remembered far longer than one you were given.

Affiliate

Preply — study more efficiently by working with a personal tutor. 50% off.

How to study Program evaluation and review technique in 20 minutes

  1. Read the reference excerpt below once, without taking notes.
  2. Close the page and write down what Program evaluation and review technique means in your own words.
  3. Compare your version with the excerpt and mark what you missed.
  4. Work through the three examples above with pen and paper.
  5. Explain Program evaluation and review technique out loud to somebody else — or to Teacher Smith in the lgStudy chat.

Frequently asked questions

What is Program evaluation and review technique in simple terms?

The program evaluation and review technique (PERT) is a statistical tool used in project management, which was designed to analyze and represent the tasks involved in completing a given project. PERT was originally developed by Charles E.

Why does Program evaluation and review technique matter?

Because it connects several engineering ideas at once: it gives you a definition you can apply, a quantity you can calculate, and a way to check whether a result is plausible.

How should I study Program evaluation and review technique?

Read the excerpt, restate it from memory, then work through the examples and applications listed on this page. The five-step study plan above takes about twenty minutes.

What does this page cover?

It gives you a compact reference excerpt plus original lgStudy explanations, examples, applications and study material on Program evaluation and review technique.

Tags

  • Booz Allen Hamilton
  • Diagrams
  • Engineering management
  • Evaluation methods
  • Management science
  • Network theory
  • Operations research
  • Project management techniques
  • Schedule (project management)
  • Systems engineering

Keep exploring