In electrical power systems, a slack bus (or swing bus, or V-δ bus) is a bus used to balance the active power | P | {\displaystyle |P|} and reactive power | Q | {\displaystyle |Q|} in a system while performing load flow studies. The slack bus is used to provide for system losses by emitting or absorbing active and/or reactive power to and from the system.
Load flow studies For power systems engineers, a load flow study explains the power system conditions at various intervals during operation. It aims to minimize the difference between the calculated and actual quantities. Here, the slack bus can contribute to the minimization by having an unconstrained real and reactive power input.
P i = P G i − P L i {\displaystyle P_{i}=P_{Gi}-P_{Li}}
Δ P i = P i − P i , c a l c {\displaystyle \Delta P_{i}=P_{i}-P_{i,calc}}
Δ Q i = Q i − Q i , c a l c {\displaystyle \Delta Q_{i}=Q_{i}-Q_{i,calc}}
The use of a slack bus has an inherent disadvantage when dealing with uncertain input variables: the slack bus must absorb all uncertainties arising from the system and thus must have the widest possible nodal power distributions. Even moderate amounts of uncertainty in a large system may allow the resulting distributions to contain values beyond the slack bus's margins. A load flow approach able to directly incorporate uncertainties into the solution processes can be very useful. The results from such analyses give solutions over the range of the uncertainties, i.e., solutions that are sets of values or regions instead of single values.
Types of buses Buses are of 3 types and are classified as:
PQ bus – the real power | P | {\displaystyle |P|} and reactive power | Q | {\displaystyle |Q|} are specified. It is also known as Load Bus. Generally, in a PQ bus, the generated real and reactive power will be assumed to be zero. However, power will be flowing out, thus, the real power and reactive power will be both negative. The Load Bus will be used to find the bus voltage and angle. PV bus – the real power | P | {\displaystyle |P|} and the voltage magnitude | V | {\displaystyle |V|} are specified. It is also known as Generator Bus or a Regulated Bus. The real power and voltage are specified for buses that are generators. These buses have a constant power generation, controlled through a prime mover, and a constant bus voltage. Slack bus – to balance the active and reactive power in the system. It is also known as the Reference Bus or the Swing Bus. The slack bus will serve as an angular reference for all other buses in the system, which is set to 0°. The voltage magnitude is also assumed to be 1 p.u. at the slack bus. The slack bus provides or absorbs active and reactive power to and from the transmission line to provide for losses, since these variables are unknown until the final solution is established. The slack bus is the only bus for which the system reference phase angle is defined. From this, the various angular differences can be calculated in the power flow equations. If a slack bus is not specified, then a generator bus with maximum real power | P | {\displaystyle |P|} acts as the slack bus. A given scheme can involve more than one slack bus.
Formulation of load flow problem The most common formulation of the load flow problem specifies all input variables (PQ at loads, PV at generators) as deterministic values. Each set of specified values corresponds to one system state, which depends on a set of system conditions. When those conditions are uncertain, numerous scenarios must be analyzed. A classic load flow analysis consists of calculating voltage magnitude and phase angle at the buses, as well as the active and reactive line flows for the specified terminal (or bus conditions). Four variables are associated with each bus:
voltage | V | {\displaystyle |V|}
phase angle | δ | {\displaystyle |\delta |}
active or real power | P | {\displaystyle |P|}
reactive power | Q | {\displaystyle |Q|}
Based on these values, a bus may be classified into the above-mentioned three categories as -